Eldorado Gold now has all four tailings filter presses required for commercial production running at its Skouries copper-gold mine in Halkidiki, northern Greece. The company is targeting commercial production by the end of 2026.

The filtered tailings facility comprises six Metso presses: five operating units and one installed spare. Four are needed for commercial production on sulphide ore and five to reach nameplate throughput.

Over a 20-year mine life, Skouries is expected to produce an average of 140,000 oz of gold and 67 Mlb of copper a year.

The project has had a long road to production. Construction began in 2013 but was suspended in 2016, and the site was placed on care and maintenance in December 2018 before work restarted.

Source: MINING.COM.