To purchase this space contact Gordon

Kouroussa construction Begins & Ongoing High-Grade Drilling Data Received
Hummingbird Resources plc (AIM: HUM) provides an update on the Company’s mine development progress and results from further assays of the 2021 Resources and Reserves infill drilling programme, including a notable hole of 24 meters (“m”) at 5.33 grams per tonne (“g/t”) amongst others, at the Kouroussa Gold Mine (“Kouroussa” or “the Project”) in Guinea.
Construction at Kouroussa has commenced following the mobilisation of equipment and personnel in December 2021. Key construction developments include :
▪ Commencement of ground clearing works for key infrastructure, mine camp and processing plant
▪ Further long lead item purchases are being finalised, including: SAG mill; jaw crusher; ore feeders; agitators; interstage screens; tower crane; and cyclone cluster
▪ The pit dewatering team is on site, and works have commenced to further stabilise the key mining deposits for future mining operations
▪ Construction equipment, tooling, machinery, and consumables continue to arrive and are in position on site for the overall build process
▪ Process plant civil works are scheduled to commence in February once more ground clearing works are completed