BHP plans to spend between US$13.6 billion and US$17.4 billion to double copper production from its Copper South Australia province to about 650,000 t/y by 2040.
The company outlined the programme on 23 November during an investor tour of its South Australian operations. It brings together Olympic Dam, Carrapateena, Prominent Hill and the Ankata deposit, formerly known as Oak Dam.
A first phase would lift output to about 500,000 t/y by 2035, with a second phase taking production to the 650,000 t/y target. Central to the plan is an expanded smelter and refinery at Olympic Dam, which treats concentrate from across the province.
Copper South Australia produced 321,000 t of copper in FY2026. BHP expects to make a final investment decision in the first half of 2027.
Source: MINING.COM / Reuters.