Endeavour Silver has published the results of a feasibility study for its Pitarrilla silver-lead-zinc project in Durango State, Mexico, outlining an 18-year underground operation with an after-tax net present value (5%) of US$736 million and an after-tax internal rate of return of 16.37%.
The study, announced on 19 November 2026, is based on a mechanised, ramp-access underground mine targeting the project’s sulphide mineralisation and high-grade core. Ore would be treated in a conventional crushing, grinding and flotation plant designed for 4,000 tonnes per day, producing separate silver-lead and silver-zinc concentrates.
Average output over the life of mine is put at around 7.5 million ounces of silver equivalent a year – roughly 5.4 Moz of silver, 13,000 tonnes of lead and 29,000 tonnes of zinc – rising to about 7.9 Moz AgEq a year over the first five full years of production.
Initial capital is estimated at about US$585 million, including US$65 million of contingency, with a further US$119 million or so of sustaining capital over the mine life. All-in sustaining costs are estimated at US$15.06 per payable ounce of silver, net of by-product credits, and the company says the project would break even at a silver price below US$30/oz. The base case assumes silver at US$50/oz. Payback is estimated at about five years after tax.
Endeavour plans a 30-month construction period. Before a development decision, which will need Board approval, the company will move into front-end and detailed engineering, place orders for long-lead equipment and continue talks with local communities and government. A permit for the tailings storage facility and other approvals are still outstanding. The supporting NI 43-101 technical report is due to be filed within 45 days.
Chief executive Dan Dickson described the results as a major milestone for the company, saying Pitarrilla has the potential to become a cornerstone asset.
Pitarrilla lies on the eastern flank of the Sierra Madre Occidental, about 160 km from both Durango city and Torreón, and covers some 4,950 hectares across five concessions. Endeavour acquired the project from SSR Mining in 2022.