India’s Ministry of Coal has issued revised guidelines for preparing mining plans and mine closure plans. Issued on 20 November, they come into force 30 days later.

Mechanised loading infrastructure is now mandatory at all coal and lignite mines, and blast-free extraction becomes the default method. Drilling and blasting will be allowed only where blast-free methods are technically unfeasible or commercially unviable, and operators must justify the choice.

Mines with a peak rated capacity of 2 Mt/y or more must include non-road coal evacuation arrangements in their mining plans, to be implemented within five years of production starting, as far as practicable.

Mine closure obligations have also been tightened. The Coal Controller can move to forfeit a mine’s escrow funds if closure activities are not being carried out. If escrow payments remain unpaid by 31 December of the following financial year, the mining plan will be suspended, and approval may be withdrawn if the dues are still outstanding six months later.

The guidelines also recognise underground coal gasification as a mining method. Mining plans submitted before the new rules take effect will remain under the January 2025 guidelines.

Source: Business Standard.